  • Project Location: 105 46th Street NE, Fort Payne, AL
  • Project Type: Ground Up Metal Building
  • Project Completion: 2011
  • Square Footage: 110,000

Heil Environmental is the world’s premier manufacturer of ultra-durable, highly productive mobile refuse collection vehicles and the industry’s leading provider of collection solutions that help customer achieve long equipment life and the lowest total cost of ownership.

Over 100,000 SF of remodel and addition work was needed at Heil’s Fort Payne facility to cover the demand of their clientele.  Two new large metal buildings were placed on site with MEP’s, concrete, site work, sprinkler, and finishes.

The office portion of this job consisted of remodeling 12,000 SF of existing office space while personnel remained working plus expanding those offices into a new 13,000 SF addition.  This included MEP’s, finishes, doors/windows, masonry, brick, EFIS, steel canopies, and concrete.  The office portion of this job is currently in review for LEED certified status through the USGBC.

The Parts Central building was a 25,000 SF metal building with offices and bathrooms that included MEP’s, structural steel, canopies, finishes, door/windows, and concrete.  The building houses Heil’s Certified OEM Parts.  They’re made following the exact specifications and production processes on the same assembly lines as the parts originally installed on the vehicles.  This means that they fit perfectly every time.  Heil uses only the highest-quality materials for parts that last- minimizing expensive downtime.  Parts Central offers Heil Certified OEM Parts and a variety of aftermarket parts manufactured by Heil.

The Mount Shop consisted of a 50,000 SF open Metal building to house refuse collection vehicle assembly line.  MEP’s, finishes, structural steel, concrete, and doors/windows were included in this phase of construction.